Site Survey for Power Plants and Substations

Print Friendly, PDF & Email

Please fill this survey in Word document, replace or attach photos and send to BatteryDAQ.

Company and Site Information

Client/Company Name: Site Name:
Plant Type:
☐ Power Generation
☐ Substation
☐ Other (specify)
Client Technical Contact:

Tel:

Cell:
Email:

Installation Address:

 

Installer:

 

Intended Installation Date:  

Battery Information

Battery type/Model:   Capacity:                 Ah
Bus Voltage:    ☐ 120V  ☐240V Battery Number in This String:
Designed Maximum Current:           A Contact BatteryDAQ if this is for Ni-Cad batteries.
Terminal/Post Bolt Size

☐ 6mm

☐ 8mm

☐ 10mm

☐ Others

Bus Cable Size: Number of Cables at Inter-Tier:

Sentry BMS mounting location

Choose one or more mounting options

Location Description
☐ Inside battery room, wall mounting  
☐ Inside battery room, mount on battery rack  
☐ Control room next to battery room, wall mounting  
☐ Other (specify)  

Photos (Very Important)

Please attach high resolution photos.

  Description Example
Photo-1

Show battery room overview

(multiple photos if necessary)

Photo-2

Show battery brand/model  
Photo-3

Show battery post/terminal and connection bar/cable  
Photo-4

Show Positive bus connection  
Photo-5

Show Negative bus connection  
Photo-6

Show Inter-Tier connection for choosing correct window size for Current Transducer

 
Photo-7

Intended BMS mounting location  
Photo-8

Show rack structure for cable tray installation  

Cable Length Estimation

Check the distance and estimate the maximum cable length. L1(ft) L2(ft) L3(ft) L4(ft) Total (ft)

                         

Dashed lines are for going under floor.

Network Connection

Available Connection Options on Site Description
☐ Ethernet with assigned static IP  
☐ Company’s Wi-Fi  
☐ 3G Router  
☐ Direct Connection between PC and BMS Specify distance between PC and BMS         (ft)